Harness Location-Specific Energy Intelligence¶
global model
Pinpoint wind and solar project potential across 67,000 US sites
Solar Cost Curve¶
Solar LCOE incl. transmission costs, capex for new technologies, and land-siting constraints
Interactive Maps
Marker size denotes potential capacity. Levelized cost of energy is described by the following color scale: green = low, yellow = medium, red = high. Zoom out to view nationwide opportunities.
Wind Cost Curve¶
Wind LCOE incl. transmission costs, capex for new technologies, and land-siting constraints
Model Components¶
-
Resources: Incorporates high-fidelity wind speed and solar irradiance data
-
Technology & Cost: Utilizes detailed assumptions for technology design and project finance
-
Siting Constraints: Accounts for physical, regulatory, and environmental restrictions
-
Grid Connection Cost: Models costs associated with grid interconnection
graph LR
A[Wind Resource] --> E[Hourly Generation];
D[Turbine Specs] --> E;
E --> F[Site LCOE];
H[Power Grid] --> I[Supply Curve];
F --> I;
G[Land Use] --> I;
Hardware Costs¶
The following technical and financial parameters serve as the baseline for the supply curve calculations. The model assumes a 30-year capital recovery period with capital expenditure estimates benchmarked for the year 2030.
| Parameter | Value |
|---|---|
| PV Array Nameplate | 1 MW |
| PV Array Type | 1-axis tracking |
| Tilt | 0 degrees |
| System Losses | 10.4% |
| Inverter Loading Ratio | 1.34 |
| Capacity Density | 43 MWdc/km² |
| Capital Expenditures | 1,042 (2021$/kWac) |
| Fixed O&M | 18.4 (2021$/kWac/yr) |
| Fixed Charge Rate | 0.06778 |
| Parameter | Value |
|---|---|
| Turbine Nameplate | 6 MW |
| Rotor Diameter | 170 m |
| Hub Height | 115 m |
| System Losses | Calculated |
| Capacity Density | Calculated |
| Capital Expenditures | 1,150 (2021$/kW) |
| Fixed O&M | 27 (2021$/kW/yr) |
| Fixed Charge Rate | 0.080373 |
Siting Constraints¶
While clear obstructions like highways and urban areas are easily excluded, the model also navigates more complex land-use challenges.
In the most restrictive scenario, the model applies environmental and national defense constraints in addition to standard exclusions for physical obstacles, protected lands, and regulatory setbacks.
Grid Connection Costs¶
The cost of connecting a project to the electrical grid is estimated by:
-
Calculating the cost of a new spur line using a least-cost-path algorithm.
-
Estimating associated network and substation upgrade costs.
Projects De-Risked
When scouting greenfield developments, this tool translates technical complexity into investment clarity.